Tuesday, 3 January 2017

Question of the day 3-1-2016

Question of the day:

A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?

a)37 ½ days           b)35 days        c)40 days     d)None

1 comment: